Lenval were successful in a tender bid for the removal of asbestos containing decommissioned air handling units, steam heating plant and hot water mains from within a fully functioning Hospital basement plant room.​Careful and strategic planning was involved to allow the plant room to remain fully operational during the removal of the redundant equipment.​
Birdcage scaffolds were erected to access some of the air handling units and to
allow them to be dismantled into manageable sections. ​The project was completed in eight rolling phases over a ten-month period, with all the removal works being undertaken from within asbestos enclosures under
fully controlled conditions. ​Constant and satisfactory re-assurance air monitoring was undertaken inside the plant room throughout the works, to re-assure members of staff that the method of removal prevented any asbestos fibres becoming airborne, and that their workplaces and themselves remained safe.

Before & After

Asbestos Experts Asbestos Experts
Asbestos Experts Asbestos Experts
Asbestos Experts Asbestos Experts